04/05/01 Inspection by the Will County EPA. A view of Indian Creek as
it flows into the culverts under the Main Injector ponds.
|
04/06/01 On a rainy Friday, we see the east leg of the diversion
channel with the silt dams removed.
|
04/06/01 Where the creek begins its flow into the diversion channel.
This photo was taken before the cannel was open - dam is under water.The
NuMI construction site is in the background.
|
04/06/01 Indian Creek just west of the diversion point. This photo was
taken on an unusually rainy day, causing fairly high water levels.
|
04/06/01 North end of the diversion at the truck crossing looking
west.The small culverts (submerged) at the crossing will be replaced by
four 24 inch culverts to permit greater flow.
|
04/06/01 North end of the channel looking east across the
truck crossing.
|
04/06/01 The west side of the diversion looking south. The contractor
is extracting rip rap from the channel, and preparing to move the channel
further to the west.
|
04/06/01The winters damage to the wall of the excavation has
brought the divesion channel perilously close to failure. The channel is
being relocated further from the excavation to prevent any drainage of the
creek into the excavated area.
|
04/06/01 Indian creek flowing from east to west, lookig east
at the point of diversion. This picture was taken just before flow
was cut-off into the creek.
|
04/06/01 Indian creek flowing west into the culvert system below the
Main Injector ponds, just before flow into the creek was diverted into
the divesion channel.
|
04/13/01 New 24 inch culverts installed under the haul road
to provide for better flow..
|
04/13/01 The diversion jst northwest of the excavated area now
shows very good flow.
|
04/19/01 A small rock damn added just upstream of the Main Ring
road to filter the creek flow.
|
07/19/01 Looking east, away from the 8 GeV berm,
excavation for re-diverting the creek back toward
its original path has begun.
|
08/16/01 Looking east at the culvert that spans the beam
tunnel, we see the small part of land that must be prepared before
the creek rediversion can take place.
|
08/23/01 The wing walls have been placed on the culverts. Preparing for
rediversion of Indian Creek
|
08/23/01 Culverts and rip-rap ready for the re-diversion
of Indian Creek.
|
09/25/01 Entry nto th culverts from the east side.
|
09/25/01 From the top of the 8 GeV berm, we look west at
Indian Creek.
|