11/17/99 The excavation is complete and a concrete box which will house
the sump pit is being formed.
|
11/17/99 A close up view of the box.
|
11/24/99 Pouring of the mud slab is under way. It is a thin layer of
cement over a gravel base in which the underdrain system has been buried.
The mud slab provides a good working surface on which to place the rebar.
|
11/24/99 This is how they get the cement into the hole.
|
11/24/99 Placing the first layer of rebar for the base slab has started.
|
11/24/99 The forms for the base slab are also being erected.
|
11/29/99 The yard hydrant has now been installed.
|
11/29/99 The first layer of rebar is now complete and the second layer
has started.
|
11/29/99 A close up view of the sump pit showing where the underdrain
system connects into it.
|
12/8/99 The forms and rebar for the base slab are now just about
complete.
|
12/8/99 This is the "box out" for the main sump pit. This is needed
because the sump will not be delivered before the base slab is poured.
|
12/10/99 Pouring the concrete for the base slab has begun.
|
12/10/99 The conveyor system for the concrete is simultaneously fed by
two cement trucks. More than 30 trucks will be needed.
|
12/10/99 A closer view of the operation below.
|
12/10/99 Here they are finishing the surface of the base slab.
|