03/03/00 Preparing the forms and rebar for the base of the entry
corridor.
|
03/06/00 The base slab for the entry corridor has been poured. This slab
will form the floor of the pit which will contain the overflow tank.
|
03/17/00 The subgrade walls of the entry corridor have been poured and
the gang forms are being removed. In the background and to the right, the
Los Alamos overflow tank can be seen.
|
03/22/00 The forms and rebar for corridor floor are now in place.
|
03/22/00 Pouring the concrete for the corridor floor.
|
03/24/00 The footings for the wing walls have been poured and rebar and
forms for the wing walls and corridor walls are being constructed.
|
03/31/00 The concrete for the corridor walls is being poured and the
forms for the entrance wing walls are being erected.
|
03/31/00 The concrete for the HVAC pad has been poured.
|
04/10/00 The forms have been removed from the corridor walls and the
concrete for the north wing wall has been poured.
|
04/12/00 The forms for the south wing wall are nearly complete.
|
04/24/00 Both wing walls are now complete.
|