04/03/00 The pieces of the steel tank arrive on site and are unloaded.
|
04/03/00 A view inside the tank vault showing the location of 10 of the
12 anchor bolts to which the tank will be attached.
|
04/04/00 The lower half of the tank support columns have been put in
place.
|
04/05/00 The first tank panel is in place and scaffolding has been
erected on the support columns.
|
04/05/00 Another view of the tank panel showing scaffolding and mounting
brackets.
|
04/06/00 Three panels are now in place.
|
04/10/00 A fourth panel has been placed and scaffolding has been added
to the other three.
|
04/11/00 Five of the 18 panels are now in place.
|
04/12/00 Eight panels are now in place and some welding has started.
|
04/13/00 The ninth panel is being placed. This is the last of the panels
connected to support columns.
|
04/26/00 The three bottom panels are now in place, including the one
with the man hole shown here.
|
04/26/00 All twelve side panels are also in place and are being welded.
|
05/02/00 The first of the three top panels is being placed
|
05/04/00 The last of the sphere panels has been put in place.
|
06/05/00 The last of the bosses and struts which will be used to support
the detector internals have been welded to the inside of the sphere and the
internal scaffolding has been removed.
|
06/05/00 This is a view of the manhole from inside the tank.
|
06/05/00 The stairway to the bottom of the tank is installed, but still
needs its inside handrail.
|
06/22/00 The tank is being hydro-tested. This invloves filling it with
water, applying a slight overpressure, and then searching for leaks.
|
06/22/00 After the initial hydro-test the water is pumped out until the
tank is half full, at which point the test will be repeated.
|
06/22/00 This shows a view of the fire hose (through which the tank is
being emptied) running up the stairs.
|
07/07/00 The inside of the tank is being grit-blasted. The silver pipe
that can be seen sticking out from the top is part of the ventilation
scheme.
|
07/13/00 Grit-blasting and priming the outside of the tank is about
half done.
|
07/13/00 Grit-blasting and priming the inside of the tank is complete,
though a lot of grit material needs to be cleaned out.
|
07/13/00 Another view inside the tank showing the boom used by the
painters to access the tank walls.
|
07/20/00 Priming of the tank is complete and application of the final
coats of Plascite has started.
|
07/20/00 A view looking down into the tank, showing the Plascite has
been applied around the bosses.
|
08/10/00 The vertical part of the fill pipe has been positioned in the
electronics room floor.
|
08/22/00 A view of the tank from inside the vault showing the completed
exterior paintwork.
|