09/22/01 The steel apparently goes up very quickly. This is progress
after one weekend, looking from south to north.
|
09/22/01 Looking from south to north at the steel erection.
|
09/22/01 Looking from east to west at the steel erection
at MI-12.
|
10/19/01 The transformer set within the containment enclosure
on the east side of MI-12.
|
10/19/01 The west side of MI-12 and continued work on the
access stairs.
|
01/03/02 Looking north inside MI-12 at the 30 Ton crane.
|
11/01/01 The structural steel frame of M-12 as seen from
the Indian Creek crossing.
|
11/01/01 The MI-12 structure just above the target eclosure.
|
11/01/01 The west side of MI-12 at the newly completed
entrance.
|
11/01/01 The east side of MI-12 showing the HVAC unit,
structural steel, retaining wall and monitoring wells.
|
11/25/01 Looking north at MI-12 over the 8 GeV Beam berm.
|
11/25/01 Using a mobile crane to mount the 30 T crane inside
of MI-12.
|
11/25/01 Painters working on the structural steel for MI-12.
|
11/25/01 Looking south along MI-12 at the painters, crane
installation, and roof work..
|
11/25/01 The 30 T crane bridge mounted in MI-12.
|
11/25/01 Electrical work taking place just above the target
enclosure.
|
11/25/01 Additional electrical work at the west entrance
to MI-12.
|
11/25/01 An interior view of the newly mounted crane bridge.
|
11/25/01 Progress toward painting the structural steel..
|
11/25/01 Putting the final touches on the crane installation.
|
11/30/01 Looking north at the MI-12 service building, with
the liner placed on the east wall.
|
11/30/01 Looking at the east wall of MI-12 from the interior.
|
12/10/01 The exterior of the MI-12 service building. The final
layer of siding is being installed.
|
12/10/01 The HVAC unit on the east side of MI-12.
|
12/10/01 The completed electrical substation on the east side of
MI-12.
|
12/10/01 A detail of duct-work tied into the HVAC unit. It appears
the final peice is a little short.
|
12/10/01 Looking north across the target hall inside of MI-12.
|
12/10/01 Some of the electrical installation along the north
wall of MI-12.
|
12/10/01 Another view, again looking north.
|
12/10/01 Installation of an anode for the decay pipe
cathodic protection system.
|
01/03/02 The new siding on MI-12, looking northwest.
|
01/03/02 New siding, HVAC, and roll-up door, looking southwest at MI-12.
|
01/03/02 Looking north along the decay-pipe region, and the power sub-station.
|
01/03/02 The south wall of MI-12 with the exterior siding not complete.
|
01/03/02 The south wall showing some of the structure used on the roof to
mount the siding.
|
01/03/02 Looking northeast at the incomplete siding on MI-12.
|
01/12/02 Blue blocks arriving at MI-12.
|
01/24/02 A visit from higher-ups!
|
01/24/02 MI-12, looking northeast at cable tray duct work, etc.
|
01/24/02 The complete exterior of MI-12.
|
01/24/02 Looking at the west exit door in MI-12.
|
01/24/02 Looking at the west exit door in MI-12.
|
02/27/02 As we look into the target pile, we can see the start of the
decay pipe. The horn and target will ultimately sit here.
|
02/27/02 A view of cabling going into MI-12. We're looking at
the north wall.
|
03/12/02 Slinging G-Blocks in MI-12.
|
04/15/02 Power supplies and control system racks covered for
conrete chipping work in the shield vault..
|
03/15/02 Plastic tent construted to keep concrete dust from enetring
MI-12 service building during the chipping operation.
|
04/15/02 Vent lines come from the tents to direct dust outdoors.
|
04/15/02 The vent lines, an intake and one outlet, just
outside of the door at MI-12 service building.
|
04/15/02 The actual chipping took place in the upper northwest
corner of the vault. It's difficult to see, but chip marks are visible
just under the temporary wood platform.
|